Week Lead Task Volunteer requirement
4/28 DB Build Basement walls, set beam and columns 14
5/5 DB Build floor system (if not slab on grade) / Form up sidewalks (if not done) 14
Roll joist, lay decking, layout walls if time permits
5/12 HC Build walls (framing) 26
Stand exterior walls, Stand as many interior walls as time allows
5/19 SB Complete all walls (framing) 26
Stand any remaining walls, Plumb and string line everything
Prepare for trusses, Run all top plate, Brace everything
5/26 ACT Stand truss system, run sub fascia Sheath roof, Wall wrap 20
6/2 ACT Windows, siding & shingles (exterior trim) 26
Install windows and exterior doors, Install fascia and soffit
Install siding components, Install siding, Start shingles
6/9 HC Windows, siding & shingles (exterior trim) 26
Install windows and exterior doors, Install fascia and soffit
Install siding components, Install siding, Start shingles
6/16 SB Siding, finish shingles and Insulation, Plumbing, HVAC 26
and Electrical Mechanical Inspections, Frame inspection
6/23 DB Subs Install sheetrock, Continue siding 26
Finish Sheetrock, Finish siding
6/30 ACT Sheetrock and siding, start painting exterior 20
7/7 TFB Install Flooring, Paint interior walls
and trim, painting exterior 14
7/14 TFB Form concrete driveway and remaining flatwork, Sub-contract
Install cabinets, interior trim/doors, Install drain flow wells 20
7/21 TFB Hang interior doors, Trim windows, Install bathroom cabinets 6
Install base
7/28 HC Interior trim/doors ,Finish incomplete work 6
Caulk all trim, prepare for paint
8/4 SB Paint walls, trim 14
Doors and trim should have been spray-painted by Habitat already
Paint walls and ceiling, Touch up doors and trim
8/11 DB Landscape 14
Establish finish grade, Plant shrubbery, install storm doors
8/18 THS Landscape 14
Establish finish grade, Plant shrubbery, install storm doors
Check all paint detail, Install door slops, clean everything
8/25 THS Clean up all unfinished tasks. 14
We do contract out some dozen jobs throughout the build. If you have professional contractors in your congregation that are able and willing to provide these services, and they are willing to provide them on our schedule, we welcome those “gifts-in-kind” contributions. Here is a list of our needs on the Concord Way project and the estimated date we would need them.
|
|
|
|
3723 Concord Way |
|
|
|
|
Doraville |
|
|
|
|
|
|
Truss & Deck Installation |
|
|
26-May |
|
Cornice Work |
|
|
9-Jun |
|
Electrical |
|
|
9-Jun |
|
Plumbing |
|
|
9-Jun |
|
HVAC |
|
|
9-Jun |
|
Roofing |
|
|
16-Jun |
|
Install Drywall |
|
|
23-Jun |
|
Supply Drywall |
|
|
23-Jun |
|
Pour & Finish Walk and Drives |
|
|
7-Jul |
|
Supply Concrete (for walks and drives) |
|
|
7-Jul |
Lead Sponsor Code:
DB – Dunwoody Baptist Church
HC – Holy Cross Catholic Church
SB – St. Bede’s Episcopal Church
ACT – ACT Investments
TFB – Tucker First Baptist
THS – Tucker High School