CONCORD WAY SCHEDULE  SPRING-SUMMER 2007

 

Week   Lead         Task                                                                          Volunteer requirement              

 

4/28       DB     Build Basement walls, set beam and columns                                                              14

 

5/5           DB          Build floor system (if not slab on grade) / Form up sidewalks (if not done)              14

                                Roll joist, lay decking, layout walls if time permits

5/12         HC          Build walls (framing)                                                                                                            26

Stand exterior walls, Stand as many interior walls as time allows

5/19         SB           Complete all walls (framing)                                                                                              26

Stand any remaining walls, Plumb and string line everything

Prepare for trusses, Run all top plate, Brace everything

 

5/26         ACT       Stand truss system, run sub fascia Sheath roof, Wall wrap                                     20

 

6/2           ACT       Windows, siding & shingles (exterior trim)                                                                 26

                               Install windows and exterior doors, Install fascia and soffit

                               Install siding components, Install siding, Start shingles

 

6/9           HC         Windows, siding & shingles (exterior trim)                                                                  26

                               Install windows and exterior doors, Install fascia and soffit

                               Install siding components, Install siding, Start shingles

 

6/16         SB         Siding, finish shingles and Insulation, Plumbing, HVAC                                            26

                             and Electrical Mechanical Inspections, Frame inspection

               

6/23         DB          Subs Install sheetrock, Continue siding                                                                        26                         

Finish Sheetrock, Finish siding

6/30         ACT       Sheetrock and siding, start painting exterior                                                                  20                 

7/7            TFB      Install Flooring, Paint interior walls

                               and trim, painting exterior                                                                                                   14        

                                                                                                               

7/14        TFB        Form  concrete driveway and remaining flatwork,   Sub-contract

                               Install cabinets, interior trim/doors,  Install  drain flow wells                                        20

               

7/21         TFB       Hang interior doors, Trim windows, Install bathroom cabinets                                       6

                                Install base

 

7/28         HC          Interior trim/doors ,Finish incomplete work                                                                        6

                                Caulk all trim, prepare for paint

 

8/4           SB           Paint walls, trim                                                                                                                      14

Doors and trim should have been spray-painted by Habitat already

Paint walls and ceiling, Touch up doors and trim

 

8/11          DB        Landscape                                                                                                                           14                               

                               Establish finish grade, Plant shrubbery, install storm doors                           

                           

 

8/18        THS       Landscape                                                                                                                          14                               

                               Establish finish grade, Plant shrubbery, install storm doors                           

                            Check all paint detail, Install door slops, clean everything

 

8/25        THS        Clean up all unfinished tasks.                                                                                             14

 

 

We do contract out some dozen jobs throughout the build.  If you have professional contractors in your congregation that are able and willing to provide these services, and they are willing to provide them on our schedule, we welcome those “gifts-in-kind” contributions.  Here is a list of our needs on the Concord Way project and the estimated date we would need them.

 

 

 

 

3723 Concord Way

 

 

 

Doraville

 

 

 

 

Truss & Deck Installation

 

 

26-May

Cornice Work

 

 

9-Jun

Electrical

 

 

9-Jun

Plumbing

 

 

9-Jun

HVAC

 

 

9-Jun

Roofing

 

 

16-Jun

Install Drywall

 

 

23-Jun

Supply Drywall

 

 

23-Jun

Pour & Finish Walk and Drives

 

 

7-Jul

Supply Concrete (for walks and drives)

 

 

7-Jul

 

Lead Sponsor Code:

 

DB  – Dunwoody Baptist Church

HC  – Holy Cross Catholic Church

SB  – St. Bede’s Episcopal Church

ACT – ACT Investments

TFB – Tucker First Baptist

THS – Tucker High School